1. [Fall 2022] What is the
purpose of providing sanitation facilities? Compare the conservancy and
water-carriage systems of sanitation, indicating the merits and demerits of
each.
2. [Spring 2020] Describe the
system of sanitation with its advantages and disadvantages. Why is the
water-carriage system of sanitation more popular than the conservancy system?
How do you collect and dispose of dry refuse in a rural area?
3. [Spring 2023] Define
sanitation. Explain the various types of sanitation systems.
4. [Fall 2024] Explain the types
of sanitation systems, highlighting their advantages and disadvantages.
5. [Spring 2021] At a
sparsely-populated place, what type of sanitary system would you use, and why?
What sewerage system would you use in a place with high rainfall intensity?
Why?
6. [Fall 2021] Define sewage and
sanitation. Compare the different systems of sanitation.
Also:
Determine the design discharge for the combined system of a small town with a
projected population of 50,000 residing over an area of 30 hectares. Rate of
water supply = 130 lpcd; permeability factor = 0.55; time of concentration = 30
min. Assume suitable data if necessary.
7. [Spring 2021] Find the
quantity of sewage for separate, combined and partially-separate systems for a
catchment area of 300 hectares, tr = 3 min, tc = 16 min. Population density =
600 persons/hectare; rate of water supply = 135 lpcd. Assume other necessary
data.
Surface
data — Roof 5% (C=0.85); Pavement & Yard 25% (C=0.81); Lawn & Garden
30% (C=0.15); Road 20% (C=0.43); Vacant Plot 20% (C=0.12).
8. [Fall 2022] Enlist the
sources of sanitary sewage. A city with a population of 100,000 has an area of
100 hectares. Find the ratio of DWF and WWF for the sewer line: rate of water
supply = 110 lpcd; average runoff coefficient = 0.52; time of concentration =
50 min; assume 80% of water supplied reaches the sewer. Comment on your result.
9. [Spring 2023] Define time of
concentration. Calculate the design discharge for a sewer: projected population
= 100,000; area = 9 sq.km; rate of water supply = 112 lpcd; permeability factor
= 60%; rainfall duration = 15 min; time of flow = 15 min; time of entry = 5
min. Assume 85% of supplied water is converted to wastewater and maximum demand
is 3 times the average demand.
10. [Fall 2024] Calculate the
quantity of wastewater generated during a storm for separate, combined and
partially-separated sewage systems, assuming an average rainfall depth of 20 cm
over 4 hours, for the given catchment area, storm duration 40 minutes.
Surface
data — Roof 25% (C=0.90); Road 12% (C=0.85); Park/Garden/Lawns 30% (C=0.20);
Yard 15% (C=0.70); Vacant Plots 18% (C=0.12).
11. [Fall 2022] Explain the
objectives of solid waste management. Suggest an appropriate solid waste
management approach for Pokhara, with justification.
12. [Spring 2023] As a member of
the development planning commission for your city, the mayor seeks your
recommendations to improve the existing solid waste management system. Provide
a comprehensive plan outlining the key strategies you would suggest.
13. [Spring 2021] As a member of
the development planning commission of Kathmandu Metropolitan City, what
suggestions would you give the mayor for solid waste management?
14. [Fall 2021] Describe
incineration as a method of solid waste disposal, with its merits and demerits.
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
Sanitary landfill
●
Solid waste management
practices
Unit II:
Quality of Wastewater
Constituents & properties · decomposition · BOD/COD ·
sampling · population equivalent
1. [Spring 2020] Write about BOD
and its significance in wastewater treatment. How is it determined in the
laboratory for domestic sewage? A test is conducted to find the relative
stability at 37°C; the incubation period to decolourise the mixture at that
temperature is 8 days. Calculate the relative stability of the sample.
2. [Spring 2020] What do you
understand by population equivalent? How do you determine it? A main combined
sewer serves an area of 12 sq.km with a population density of 250
persons/hectare. Average wastewater flow = 85 lpcd; peak flow is 80% in excess
of average, together with a rainfall equivalent of 40 mm in 24 hrs (70%
runoff). Calculate the capacity and size of the combined sewer (max. velocity
2.8 m/sec).
3. [Fall 2021] What do you mean
by sampling of wastewater? Determine the 2-day BOD at 20°C for a sewage having
a 5-day BOD at 20°C of 180 ppm (base-10 rate constant = 0.1/day).
4. [Spring 2021] Differentiate
between BOD and COD. With a sketch, explain how nitrogenous organic matter
changes from one form to another.
5. [Spring 2021] If the 5-day
BOD at 20°C is 280 mg/l and the 1-day BOD at 25°C is 111.80 mg/l, calculate the
rate reaction constant 'k' at 20°C and the 7-day BOD at 25°C.
6. [Fall 2022] Explain the
sampling procedure for sewage. Also explain, in detail, the procedure for
finding the BOD of a sewage sample in the laboratory.
7. [Spring 2023] How do you
determine the DO of a wastewater sample in the laboratory? Explain with an
appropriate example.
8. [Spring 2023] What are the
limitations of the BOD test? If the 3-day BOD at 28°C of a sewage sample is 350
mg/lit, what will be its 5-day BOD at 38°C? (K = 0.1/day, base-10, at 20°C).
9. [Fall 2024] What do you
understand by wastewater sampling? Calculate the 2-day BOD at 30°C for a sewage
with a 5-day BOD of 280 ppm, assuming a base-10 rate constant of 0.1/day at
20°C.
10. [Fall 2024] What are the
limitations of the BOD test? How do you determine the BOD of a wastewater
sample in the laboratory? Explain in detail.
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
Aerobic and anaerobic
decomposition
●
Nitrogen and carbon
cycles
Unit III:
Design and Construction of Sewer
Hydraulics of sewer flow · self-cleaning velocity · sewer
materials · sewer appurtenances
1. [Fall 2021] Design a sewer
running 0.7 times full at maximum discharge for a city with population 120,000
and per-capita water supply 180 l/day. Design the circular sewer taking N =
0.013, slope = 1/500, peak factor = 2.25 (80% of water supply contributes to sewage).
2. [Spring 2021] If the sewer
runs 0.8 times full at maximum discharge, design the circular sewer (N = 0.013,
slope = 1 in 600, peak factor = 2.5, 85% of water supply contributes to
sewage). Also design a sewer to serve a population of 20,000 with a water
supply of 200 lpcd.
3. [Fall 2022] What are the
requirements of sewer materials? What hydraulic analyses are carried out for
sewer design? Explain.
4. [Fall 2022] Design a sewer
running 0.75 times full at maximum discharge for a town of 150,000 persons on a
separate system, water supply 250 lpcd, n = 0.013, permissible slope 1 in 500,
peak factor 3.
5. [Spring 2023] Find the
minimum velocity and gradient required to transport coarse sand particles of
0.8 mm diameter and specific gravity 2.62 through a sewer of 1.5 m diameter (β
= 0.1, f = 0.03, sewer running half full, n = 0.012).
6. [Fall 2024] A circular sewer
and a rectangular sewer are hydraulically equivalent. Find the relation between
the depth of the rectangular sewer and the diameter of the circular sewer, if
the width of the rectangular sewer is 2.5 times its depth (rectangular sewer
open to atmosphere).
7. [Fall 2024] What do you
understand by self-cleaning velocity? Explain its significance in sewer design.
Derive Shield's expression for self-cleaning velocity.
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
Crown corrosion in sewer
pipeline
●
Manhole
●
Requirements of sewer
materials
Unit IV:
Disposal of Wastewater
Dilution method · self-purification · oxygen sag curve &
Streeter–Phelps equation
1. [Spring 2020] Using the given
river/wastewater data (flow, DO and BOD for the river and the wastewater; k =
0.12/day, R = 0.40/day), find the DO at the end of 2 days after mixing.
2. [Fall 2021] A town discharges
130 m3/sec of sewage into a river that is 85% saturated with DO and flows at
1600 m3/sec during the lean period (velocity 0.12 m/sec). The 5-day BOD of the
sewage is 310 mg/L. Find the critical DO deficit and when/where it occurs
downstream (k = 0.11/day, self-purification coefficient f = 4, saturation DO at
20°C = 9.17 mg/lit, ultimate BOD = 130% of 5-day BOD).
3. [Spring 2021] A city
discharges 100 cumecs of sewage into a river fully saturated with oxygen,
flowing at 1500 cumecs during the lean period (velocity 0.1 m/s). The 5-day BOD
of the sewage is 280 mg/lit. Find when and where the maximum DO deficit will
occur downstream, and its amount (self-purification coefficient = 4.0,
saturation DO at 20°C = 9.2 mg/lit, k = 0.1/day).
4. [Fall 2022] A city discharges
1500 lps of sewage into a stream with a minimum flow of 5000 lps (both at
20°C). The 5-day BOD of the sewage is 180 mg/l and of the river is 2 mg/l.
Sewage DO is zero; river DO is 90% of saturation. If the minimum DO to be
maintained is 4.5 mg/l, find the degree of sewage treatment required
(deoxygenation coefficient 0.1/day, re-oxygenation coefficient 0.3/day,
saturation DO at 20°C = 9.17 mg/l).
5. [Spring 2023] A river with
fully-saturated DO receives sewage at 120 cumecs; the river flow is 1800 cumecs
at a minimum velocity of 0.2 m/s. Find the critical DO deficit and its location
(5-day BOD at 25°C = 300 mg/l, coefficient of purification = 0.12/day, ultimate
BOD = 380 mg/l).
6. [Fall 2024] Determine the
degree of treatment required to maintain a minimum DO of 4 mg/l in a stream
when a town discharges 800 lps of sewage (5-day BOD = 250 mg/l) into a stream
with minimum flow 4000 lps; river DO is 80% of saturation (K1 = 0.1/day, K2 =
0.3/day, saturation DO at 20°C = 9.17 mg/l).
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
Oxygen sag curve
●
Sewage sickness
Unit V:
Physical and Chemical Treatment of Wastewater
Treatment layout · screening · skimming/flotation tank · grit
chamber · sedimentation
1. [Spring 2020] Design a grit
chamber for a treatment plant expecting an average flow of 5000 m3/h of
domestic wastewater; determine the effective and overall dimensions. With a
neat sketch, describe the purpose and construction of a grit chamber.
2. [Fall 2021] Design a grit
chamber for a sewage flow of 50 MLD (specific gravity of grit = 2.65,
temperature 28°C, particle size 0.21 mm, specific gravity of organic matter =
1.2, k = 0.06, f = 0.03).
3. [Spring 2021] Why should
wastewater be treated? What processes are involved?
4. [Fall 2022] Draw the typical
layout of a wastewater treatment plant. Explain the different primary and
secondary treatments of wastewater.
5. [Fall 2022] Design a grit
chamber for a sewage flow of 55 MLD (specific gravity of grit = 2.65,
temperature 27°C, particle size 0.21 mm, specific gravity of organic matter =
1.2, K = 0.06, f = 0.03).
6. [Fall 2024] Design a grit
chamber for a wastewater treatment plant for a population of 250,000, flow rate
100 lpcd, specific gravity of grit = 2.65, specific gravity of organic particle
= 1.2, particle size 0.2 mm, temperature 20°C, peak factor 2.5.
7. [Fall 2024] How are fats, oil
and grease removed from wastewater? Write the design steps for such a unit.
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
Purpose and construction
of a grit chamber
●
Preliminary treatment
units
Unit VI:
Biological Treatment of Wastewater
Trickling filter · activated sludge process · oxidation pond
1. [Spring 2020] Write briefly about
the biological unit of a wastewater treatment plant, with an example. Calculate
the effluent BOD of a two-stage trickling filter (sewage flow 5 MLD, influent
BOD in first TF = 350 mg/lit, volume of first filter = 800 m3, volume of second
filter = 400 m3, recirculation 1.8 & 1).
2. [Fall 2021] Explain the basic
operation involved in the activated sludge process, with the help of a flow
diagram.
3. [Fall 2021] Calculate the
effluent BOD of a two-stage trickling filter (sewage flow 5 MLD, influent BOD
in first stage = 350 mg/lit, volume of first filter = 650 m3, volume of second
filter = 400 m3, recirculation ratio of both filters = 2).
4. [Fall 2021] Design an
oxidation pond to serve a community removing 90% of influent BOD, population
3500, sewage flow 150 lpcd, permissible organic loading 510 kg/ha/day, influent
BOD 250 mg/lit (rate constant 0.1/day).
5. [Spring 2021] Design a
high-rate single-stage trickling filter for a town of 40,000 persons: domestic
sewage @ 150 lpcd (200 mg/l BOD), industrial wastewater @ 0.25 MLD (600 mg/l
BOD), recirculation ratio 1.0, BOD removal in primary clarifier 35%, effluent
BOD desired 30 mg/l.
6. [Spring 2021] What is meant
by activated sludge? Describe, with a schematic diagram, the treatment of
wastewater by the activated sludge process.
7. [Fall 2022] Calculate the
diameter required for a single-stage trickling filter to yield an effluent BOD5
of 20 mg/l, treating settled domestic sewage of BOD5 120 mg/l (flow 2200
m3/day, recirculation 4000 m3/day, filter depth 1.5 m).
8. [Spring 2023] Design an
oxidation pond for sewage from a population of 4000 @ 160 lpcd (5-day BOD 310
mg/l, organic loading 350 kg/ha/day, width:length 1:2, operational depth 1.25
m).
9. [Spring 2023] Differentiate
between attached-growth and suspended-growth processes; mention the various
treatment techniques included in each. Also design a high-rate two-stage
trickling filter for a town of population 52,000 (domestic sewage @ 165 lpcd,
210 mg/l BOD; industrial sewage @ 0.25 MLD, 790 mg/l BOD; BOD removed in
primary clarifier 35%; effluent BOD desired 25 mg/l).
10. [Fall 2024] Design a
high-rate two-stage trickling filter for a town of population 52,000 (domestic
sewage @ 200 lpcd, 200 mg/l BOD; industrial sewage @ 0.5 MLD, 800 mg/l BOD; BOD
removed in primary clarifier 35%; effluent BOD desired 25 mg/l).
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
Compare normal-rate and
high-rate trickling filters
●
Construction, location
and working of an oxidation pond
Unit VII:
Treatment of Sludge and Disposal
Sludge sources · thickening · dewatering · digestion · disposal
methods
1. [Spring 2020] Differentiate
between conventional and high-rate digesters. Explain the effect of temperature
and pH on the anaerobic digestion process. Briefly explain dewatering by sludge
drying beds and rotary vacuum filtration. Is dewatering of sludge necessary?
2. [Fall 2021] Briefly describe
the aerobic and anaerobic sludge digestion processes. Explain the effect of pH
and temperature on the digestion process.
3. [Spring 2021] Design a sludge
digestion tank from the given data: capacity of sedimentation tank = 800 m3,
detention time 2.5 hrs, SS in raw sewage 240 mg/l, W/C in digested sludge 80%,
W/C in fresh sludge 93%, specific gravity of sludge 1.04, digestion period 4
months, PST removes 40% SS.
4. [Fall 2022] Why is it
necessary to treat sludge? Explain the different sludge-treatment procedures.
5. [Fall 2024] Why does sludge
need to be treated? List the methods of sludge treatment. With a sketch,
elaborate the gravity thickening process and show the relationship between
volume and moisture content.
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
Sludge drying bed
●
Methods of sludge
disposal
Unit VIII:
Disposal of Wastewater in Unsewered Area
Pit privy, VIP latrine, pour-flush latrine · septic tank · soak
pit / drain field
1. [Spring 2020] What
modification was made in the VIP latrine compared to the pit latrine? Is a
septic tank an on-site or off-site sanitation option? Explain. Design a septic
tank for a house with your family's number of members (sewage rate 100 lpcd,
sludge cleaned once in 2 years); if the percolation rate is 40 min/cm, design
the drain field / soak pit (GWT 4.5 m below ground).
2. [Fall 2021] Design a septic
tank for 15 users (sewage flow 105 lpcd, sludge cleaned once in 3 years,
percolation rate 30 min/cm); design the drain field / soak pit (GWT below 5 m).
3. [Spring 2021] Design a septic
tank and soak pit for a household of 8 persons (sewage generation 100
l/person/day, septic tank cleaned once in 3 years, soil infiltration rate 50
l/m2/day).
4. [Fall 2022] Design a septic
tank for a hostel: 150 users, peak discharge 200 lpcd, desludging period 1
year, percolation rate 20 min/cm.
5. [Spring 2023] Design a septic
tank for a small colony of 350 persons, average daily sewage flow 180 l/head,
detention period 1.5 days, cleaning interval 6 months.
6. [Fall 2024] Design a septic
tank and soak pit for a household of 20 persons (150 l/person/day, retention
time 24 hrs, cleaning period 3 years, soil infiltration rate 400 l/m2/day).
Short notes commonly
asked from this unit (attempt any two, 2×5 marks — typical pattern):
●
VIP latrine
●
Leaching cesspool
●
Design considerations of
a septic tank